Six people paint the fence and 15 hours how long would it take five workers to do the same job

Respuesta :

somaiasult2006
somaiasult2006 somaiasult2006
  • 02-01-2019
it will take 12.5 hrs for five workers to do the same job.


steps:

15 × 5 = 75

75 ÷ 6 = 12.5
Answer Link

Otras preguntas

What is the distance between (-2, 4) and (5, 4) on a coordinate grid?
What is your opinion of this statement? Limits are only limits if you accept them as such. Agree Disagree Explain why you voted the way you did.
Jasmine got a prepaid debit card with $25 on it. For her first purchase with the card, she bought some bulk ribbon at a craft store. The price of the ribbon was
What is 1 + 1 x 3 Whoever answers it to
need na need na po plssss.​
As individuals age, there is a decrease in peripheral vision. a. True b. False
answet please and please show work
I hate these types of problems I was never taught this stuff
Find the area. Do you multiply all sides?
Good evening! Can someone please answer this, ill give you brainliest and your earning 50 points. Would be very appreciated.