If BAC is $ 85,000, Duration is 75 days, PV is $ 21,000, AC is $ 20,000, and % Complete is 27 %, what is the state of the project?
a. Under budget, behind schedule
b. Over budget, ahead of schedule
c. Under budget, ahead of schedule
d. Over budget, behind schedule

Respuesta :

Otras preguntas

On a desk there are 6 sheets of blue paper, 4 sheets of yellow paper, 5 sheets of green paper, and 2 sheets of pink paper. In how many ways can the paper be sta
What role should the government have in enforcing equal rights for Americans?
What is the complete predicate of the following sentence?sharon and Jason went for a walk then a bike ride
To make curtains for a living room window for a customer, you will need three pieces of fabric in the following lengths: 3 feet, 3 feet, and 5 feet. What is th
How do figure out 120/f = 1.2?
What is the sales rate for 5% of $50
Solve: K= 2(11 - k) + 14
I am so confused about this graphing problem, just need answer doesn't have to show workRectangle ABCD has a length of 9 and a width of 7. Point D is the ordere
what are the steps to evaporation but without heat just evaporation steps to follow
Translucent definition: __________ is allowed to pass through translucent objects.