If it takes 100 minutes to complete a circuit, demand at the next work center is 5 parts per minute, and a kanban container holds 20 parts, how many containers are required?

Respuesta :

miamonroe56
miamonroe56 miamonroe56
  • 02-06-2017
5 times 100 = 500
500 divided by 20 = 25
25 containers
Answer Link

Otras preguntas

Production costs of producing one more unit of output are called
Pretty dumb question, but what colour writing should I do for this?
The primary organ responsible for absorption of the products of digestion is the:
According to McClelland's Acquired Needs Theory, the need for __________ reflects an individual's desire to surpass others or accomplish something difficult.A.
Simplify to create an equivalent expression. -k-(-8k+7)
Some versions of the play have “sullied" instead of “solid.” Howdoes that change alter the focus of Hamlet's disgust?​
You are a loan officer at a bank. An application comes to you for $5000 loan. Explain why you would want to know the persons credit history
Helpppp me 10 pointssss
i dont know whats the answer can someone help me ?
Which of the following most accurately describes the extent of Alexander the Great's empire? 1. From Greece and Egypt to the Middle East and northeastern pa