If 24 electricians can wire some new houses in 15 days, how many electricians would be required to do the job in 12 days?.

Respuesta :

shishirshrestha989
shishirshrestha989 shishirshrestha989
  • 04-01-2022

Answer:

here,

electrician/days

24 - 15

x(let). -12

direct proportion,

then,

exchange X up 24 down

or,24*15=12*X

or,24*15divided by 12=X

X=30

hence,30 electrician required to do complete in 12 days

Answer Link

Otras preguntas

Compute the value of the discriminant and give the number of real solutions of the quadratic equation. 4x^2-7x+2=0
Which radical expression is an irrational number? A. ∛216 B. ∛144 C. ∛64 D. ∛125
A line that passes through the origin and point (-3,6)
Please help I will mark Brainly!
On a sunny afternoon, the Stratosphere Tower casts a shadow that is 140 meters long. At the same time, a nearby flagpole that is 10 meters tall casts a shadow t
What is the Value of x?
In which part of an interview would you have informal conversation to build rapport? Opening body closing
need this urgentlywill give brainliest
Gasoline pump delivers 4 2/5 gallons of her minute how many minutes will it take to thaw a gas tank that holds 16 1/2
What should you always do before choosing a final business name? A ) Check its frequency on a Web browser. B ) See if the domain name is available. C ) Run the