if 10 man can work 6hours.How many more men are needed towork in 4 hours​

Respuesta :

mathstudent55
mathstudent55 mathstudent55
  • 03-12-2021

Answer:

5 more men

Step-by-step explanation:

10 men do a job in 6 hours.

To do the job in 2 hours, 1/3 of the time, you need 3 times as many men.

30 men do a job in 2 hours.

To do the job in twice the time, 4 hours, you need half the men.

15 men do a job in 4 hours.

15 men - 10 men = 5 men

You need 5 more men.

Answer Link

Otras preguntas

Which best explains the reason for daily high and low tides? A. Warm, less-dense water rises, moving cold dense water toward the shore. B. Volcanic
If a state rejects an amendment, can it later approve it?
During the Antebellum period, many African Americans in the north
Order the group of quadratic functions from widest to narrowest graph y=3x^2,y=x^2,y=2x^2
What did the United States and its allies hope to accomplish through the formation of SEATO?
Using context to figure out the meaning of an unfamiliar word is useful when _____. a dictionary is available the words, phrases, and sentences surrounding the
An employee who wishes to find employment in a particular geographic location would look to which section of an occupational description? Select the best answer
ummmmm......what? how do I do this??
How does John treat the two dogs and cat that are staying with him?
Can someone please help me with this question?