Karenbrph7391 Karenbrph7391
  • 04-06-2021
  • Mathematics
contestada

For a process, the average range for all samples was 5 and the process average was 25. If the sample size was 10, calculate UCL for the R-chart.

Respuesta :

fichoh
fichoh fichoh
  • 07-06-2021

Answer:

8.885

Step-by-step explanation:

Given that :

Sample size, n = 10

The average range, Rbar for all samples = 5

The upper control limit, UCL for the R-chart is :

UCL L= D4Rbar

From the control chart constant table, D4 = 1.777

Hence,

UCL = 1.777 * 5

UCL = 8.885

The UCL for the R-chart is 8.885

Answer Link

Otras preguntas

Ancient Egyptians believed that when a person died, they went to the Field of ________, a paradise that closely resembles Earth.
The figure below shows a partially completed set of steps to construct a rhombus PQRS: Two equal sides of a rhombus PQRS are drawn. PQ that makes an acute angl
what word contains the ketters N and Y and a?
If f(x)=3x2-5 and g(x) =-2x+5, then f(3)g(3)=?
The triangle is an equilateral triangle. Write an equation and solve for x.
Which client statement indicates knowledge deficit r/t substance use disorder?a) Although legal, alcohol is one of most widely used drugsb) Tolerance to heroin
Associer chaque équation inéquation a sa représentation graphique
grade 12 speech topics​
There are 1800 pupils in a school. 20% of the pupils are in Year 8. 65% of the Year 8 pupils are girls. How many Year 8 girls are there in the school?​
Tropical sites monsoon and north east monsoon pie chart or bar graph