A critical activity is________________.a. an activity that consumes no time but shows precedence between events. b. a milestone accomplishment within the project. c. an activity with zero slack. d/ the beginning of an event.

Respuesta :

Ritmeks
Ritmeks Ritmeks
  • 09-03-2020

Answer:

C

Explanation:

Critical activity is the sequential activities from beginning to the end of a project. A lot of projects have a single critical path, although some projects may have more than one critical activity which depends on the flow logic utilized in the project.

Answer Link

Otras preguntas

Prove that (x^5)-(x^2)+2x +3=0 has at least one real root. Prove that x=cosx has at least one solution.
Find Domain of the functionsquare root of (x-8)/x(x-9)
Can someone use the word delta in a sentence
how is mass transit in cities a possible solution tk urban air pollution?
(10y^3+20y^2+55y)/5y
how is mass transit in cities a possible solution tk urban air pollution?
Scarcity is the condition of not having enough goods and services to satisfy everyone's?
Scarcity is the condition of not having enough goods and services to satisfy everyone's?
find an equivalent expression without parentheses -(50x-15y+15)=
Scarcity is the condition of not having enough goods and services to satisfy everyone's?