Estimate the quantity of soil to be excavated from the borrow pit​

Respuesta :

lola2487
lola2487 lola2487
  • 04-08-2019

Answer

1056

Explanation:

for example

A soil is to be excavated from a borrow pit which has a density of 1.75g/cc and water content of 12%. The G is 2.7 the soil is compacted to that water content of 18% and dry density of 1.65g/cc. for 1000 m3 of soil used in fill estimate

Quantity of soil to be excavated from pit in m3

Answer Link

Otras preguntas

this question is about Ratio tables help I'm struggling​
Where do teenagers get all the money they need to make purchases? I noticed several new stores had opened up at the local mall. Most of these new stores focused
someone please help me and fast if you can:(
The founders of a new nation with a population of 5 million people are considering how to construct their government. Reasoning that it would be impractical for
Simplify -1.5(-3.6+2) Pleaseee people
Using the equation x= 12- 3y, complete the ordered pair (___,-5).
here u go the question ​
WILL GIVE BRAINLIEST! PLEASE HELP! 7th grade math
can someone do a prank for me ?
4 avocados cost $0.76 At this rate, how much do 9 avocados cost?