  • Mathematics
contestada

a contractor estimates that he can paint a house in 5 days using 6 men. if he actually uses 5 men for the job, how many days will they take to paint the house?

Respuesta :

Einstein08 Einstein08
  • 01-09-2018
it will take 4 days to paint the house with 5 men
Answer Link
tramserran
tramserran tramserran
  • 01-09-2018

1 house = 6 men x 5 days  = 30 man days

Need 30 man days with only 5 men: 30x = 5 men   →  x = 6

It will take 6 days for 5 men to complete the job.

Answer: 6 days


Answer Link

Otras preguntas

Which two statements are true?
Calculate the magnitude of the gravitational force exerted on a 4.20 kg baby by a 100 kg father 0.200 m away at birth (he is assisting, so he is close to the ch
NEED HELP ASAP! The graph gx is a translation of the function fx=x2. The vertex of gx is located 5 units above and 7 units to the right of the vertex of Fx. Whi
Which is an act of violence that can occur during daiting
2 Points What is the measure of the radius of OM? A. 14.8 units 10.5 B. 10.5 units 10.5 c. 21.0 units D. 5.25 units
BRAINLIEST!!!!! match each equation with the correct type of function. n/m=1.5 v=1/3bh y=-7 vw=-18 inverse variation step functi
can someone do this for me asp for 50 points choose from one of the following topics for your newsletter: Science project Science report State report Country
An active movement where an input of energy is required. Partides move from low concentration to high concentration
A certain gasoline engine has an efficiency of 35.3%. What would the hot reservoir temperature be for a Carnot engine having that efficiency, if it operates wit
I need help, please & thank you